 In project management,a (  ) is a list of a project’s milestones,activities,and deliverables,usually with intended start and finish dates. Those items are often estimated in terms of resource allocation,budget and duration, linked by dependencies and scheduled events.

作答
schedule
WBS
SOW
charter