Project Time Management includes the processes required to manage timely completion of the project, these processes interact with each other. (  )is following the process- Estimate Activity Durations.
 

作答
Develop Schedule
Estimate Activity Resources
Define Activities
Sequence Activities
答案/解析
查看试卷及答案