What does a CPl of 80% mean?( ).
作答
As ofnow we expect the total project cost of 80% more than planned
When the project is completed, we will have spent 80% more
Your project is only progressing at 80% ofthat planned
Your project is only gett,ing 80 cents out of
答案/解析