What is incorrect about the description ofthe critical path( ).(单选题,1 分)

作答

The critical path determines theshortest possible projectduration

The critical path is the longestsequence of activities in aproject

There is only one critical path inthe progress network diagram

The critical path is constantlychanging during the projectprogress process