What is incorrect about the description ofthe project integration managementprocess ( )(单选题,1 分)

作答

Project integration managementincludes the work carried out toidentify, define, combine, unify,and coordinate various processes and activities of project management process groups

In project integration management, contract closure occurs before administrative closure. Procurement audits and contract closure must be conducted first, followed by administrative closure

Progress forecasts, approved change requests, cost forecasts, and project management plans are inputs for monitoring project work

The overall requirements of the project, the approval requirements of the project, and the main risks of the project belong to the output of formulating the project charter